Case Studies

Bank Street Basin, Coatbridge

Dredging Canal Basin

bank street basin
Contract:
Bank Street Basin, Coatbridge
Client:
North Lanarkshire Council
Designer:
The Paul Hogarth Company
Contract Value:
£1.2M
Contract Form:
ICE 5th Edition
Contract Duration:
2009/10, 30 weeks

Details:

Dredging existing canal basin, earthworks, drainage, concrete block & slab paving, resin bound gravel surfacing, blacktop works, sports surfacing, cast stone walling, steps & piers, lighting, furniture, soft landscaping & landscape maint.

Key Issues:

Co-ordination with other contractors, liaison with 3rd parties (Scottish Water & NWR), managing artworks install.