Case Studies
Greenknowes Windfarm
Slope Stabilisation
- Contract:
- Greenknowes Windfarm Slope Stabilisation
- Client:
- Scottish Power Rrenewables
- Designer:
- Fairhursts
- Contract Value:
- £150,000
- Contract Duration:
- 3 Weeks
Project Description
Install compound and spoil tip.
Scale 8500m2 of cut slope adjacent to windfarm access road. Re-profile interface at crest.
Clear and re-profile 1500m of storm drain. Vactor culverts and road crossings.
Install 7500m2 of rock-fall protection netting & erosion protection system.
Install 170No face anchors.
Hydro-seed slope.
Key Issues
- Communications
- Remote Working
- Public Interface
- Conflicting Activities in Windfarm