greenknowes windfarm
Contract:
Greenknowes Windfarm Slope Stabilisation
Client:
Scottish Power Rrenewables
Designer:
Fairhursts
Contract Value:
£150,000
Contract Duration:
3 Weeks

Project Description

Install compound and spoil tip.

Scale 8500m2 of cut slope adjacent to windfarm access road. Re-profile interface at crest.

Clear and re-profile 1500m of storm drain. Vactor culverts and road crossings.

Install 7500m2 of rock-fall protection netting & erosion protection system.

Install 170No face anchors.

Hydro-seed slope.

Key Issues

  • Communications
  • Remote Working
  • Public Interface
  • Conflicting Activities in Windfarm