Lime Tree Walk, Alloa

Construct Cycle Path

lime tree walk
Contract:
Lime Tree Walk, Alloa
Client:
Ian White Associates
Designer:
The Paul Hogarth Company
Contract Value:
£1.89M
Contract Form:
ICE 5th Edition
Contract Duration:
2009, 32 weeks

Details:

Reconstruction of existing roads & footways, construct new cycle & foot path and car park. Comprising site prep, surface water drainage, drainage connections, natural stone sett work, kerbing, surfacing, lining, block paving, sandstone walling, metal railings, street furniture & lighting and soft landscaping.

Key Issues:

Co-ordination with adjacent PFI school project, liaison with local residents & traders, removal of mature DDD trees.