Case Studies

Falmer Cutting

Soil Nailing Works

falmer cutting
Contract:
Falmer Cutting
Client:
BAM Nuttall
Designer:
Capita Simonds
Contract Value:
£300k
Contract Form:
NR 8
Contract Duration:
14 weeks

Project Description / Scope of Works

The works at Falmer Cutting (Brighton) consisted of soil nailing works to a railway cutting up to 13m high on ELR: BTL between 2m62ch and 3m49ch.

In order to maximise mid-week working, a catch fence was installed at the toe of the cutting for soil nails installation using a 20t excavator from the cutting crest.

The remainder of the works were carried out using RRV mounted rig during possession.

A total of 2200m of soil nails combined with 4500m² of netting were installed as part of this project.

All works were completed within programme & budget, and without any accident or incident.

Key Issues

  • Derive methodology/temporary works design to maximise non possession working.
  • Management of large workforce in short timescales.