Case Studies
Fauldhouse Station
Footbridge Renewal
- Contract:
- Fauldhouse Station - Footbridge Renewal
- Client:
- Network Rail
- Contractor:
- QTS Rail
- Contract Value:
- £781,000
- Contract Duration:
- Jul 2011 - Sep 2011
Project Description
The purpose of the works was to renew the life expired Footbridge that allows access between both Platforms. Project works included site investigation, open hole piling, new foundations and footbridge removal.
Key Issues
- Works within an operational Station
- High Street environment working through use of Hoarding
- Installation of Piles adjacent to live lines
- Crane Lift