Fauldhouse Station

Footbridge Renewal

fauldhouse station
Contract:
Fauldhouse Station - Footbridge Renewal
Client:
Network Rail
Contractor:
QTS Rail
Contract Value:
£781,000
Contract Duration:
Jul 2011 - Sep 2011

Project Description

The purpose of the works was to renew the life expired Footbridge that allows access between both Platforms. Project works included site investigation, open hole piling, new foundations and footbridge removal.

Key Issues

  • Works within an operational Station
  • High Street environment working through use of Hoarding
  • Installation of Piles adjacent to live lines
  • Crane Lift