Case Studies
WCML Earthworks
West Coast Main Line Works
- Site:
- WCML Earthworks
- Date:
- Dec 2009 to June 2010
- Value:
- £620k
- Client:
- Network Rail
- QTS Status:
- Principal contractor
Details:
Design and build. West Coast Main Line, Works to stabilise cuttings. Rock and soil stabilisation works, building of retaining walls and drainage works.