Oban

Geotechnical Case Study

Managing 8 different sites on the Oban line spread over 12 miles was a test in logistics.  Time on site during this design & build project was minimised by ensuring continuous work for our IRATA teams.  As the design of each slope was carried out in parallel with the de-vegetation and scaling, our Designers from Fairhurst had to hit programme dates to allow QTS to install 22,000m2 of mesh, 80m of catch-fence and drainage solutions.