The purpose of the works was to renew the life expired Footbridge that allows access between both Platforms. Project works included site investigation, grouting coals seams, open hole piling, new foundations and footbridge install and removal.

The team had to face numerous issues including, live works within an operational station and high street environment. Working through use of Hoarding, Grouting of Coal Seams, the Installation of Piles adjacent to live lines and manage Crane Lifts safely.