Midland Mainline Electrification
Fencing Case Study
QTS were Sub-contracted to SPL to renew boundary fencing and carry out lineside vegetation management to facilitate electrification and upgrade works in April of 2019.
The works included:
- Multiple design packages with varying fencing requirements.
- In excess of 91,000m fencing installed of various Class 1, 2 and 3 type.
- 28 miles vegetation clearance both sides of the railway.
QTS completed initial fencing design using Network Rail standards promoting Early Contractor Involvement.